Milestones of Amplio Hotel Investmets. Click on the date you'd like to examine.
February, 2010
Construction of HGI Golden Horn has been started.
January, 2010
Construction permit issued from Beyoğlu Municipality. Final Loan Agreement for HGI Golden Horn has been signed.
December, 2009
İstanbul Metropolitan Municipality approval obtained for HGI Golden Horn Project.
November, 2009
Start given for creation of a holding structure.
October, 2009
Total demerger process has been successfully completed. Amplio Emlak Yatırım A.Ş. / Amplio Diyarbakır Hotel Yatırım A.Ş. / Amplio Istanbul Hotel Yatırım A.Ş. are oficially registered.
September, 2009
Financing secured. Term sheet for debt financing of HGI Golden Horn has been signed.
July, 2009
Approval obtained from T.C. Tourism Ministry Cultural and Natural Heritage Board (Preservation Board) for İstanbul Haliç Hilton Garden Inn Project.
April, 2009
Capital increase to 26,500,000 TL.
January, 2009
The winner of the Hilton Istanbul - Golden Horn Architectural Competition has been announced.
October, 2008
Management Agreement signed with Hilton Hotels for Corlu site.
Management Agreement signed with Hilton Hotels for Corum site.
September, 2008
Management Agreement signed with Hilton Hotels for Istanbul-Golden Horn site.
July, 2008
Site Purchase Agreement signed for Corum site.
June, 2008
Site Purchase Agreement signed for Corlu site. David McBain appointed as the Asset Management Advisor.
May, 2008
Site Purchase Agreement signed for Istanbul-Golden Horn.
April, 2008
Management Agreement signed with Hilton Hotels for Manisa site. Management Agreement signed with Hilton Hotels for Bursa site.
March, 2008
Site Purchase Agreement signed for Manisa site. Site Purchase Agreement signed for Bursa site. Capital increase from TRY 5,000,000 to TRY 25,000,000.
January, 2008
Company name changed as "Amplio Hotel Investments Emlak A.S."
December, 2007
Strategic Development Alliance signed with Hilton Hotels. Management Agreement signed with Hilton Hotels for Diyarbakir site.
November, 2007
Site Purchase Agreement for Diyarbakir site.
September, 2007
Capital increase from TRY 1,000,000 to TRY 5,000,000. Letter of Understading signed with Hilton Hotels.
May, 2007
Amplio founded with TRY 1,000,000 capital. Lou signed with Hilton Hotels Corporation.